A public consultation on the future of Forster Square station has resulted in an 85% approval rate for the new look.
The current building will be replaced, as will the lift and staircase as part of a £17 million redevelopment scheme. The short public consultation in December resulted in 340 online and 400 paper responses.
A process to procure services will begin within weeks/months, and the aim is to complete the project by Spring/Summer 2021.
The scheme is being financed by the West Yorkshire Combined Authority’s transport fund.